RUSKLIMAT · project in progress

From material-flow balancing
to digital shift management

An integrated decision-support system for a network of distribution centers. The project develops in stages: flow first, then workforce, then shift assignment and operational control.

Flow PlanningWorkforce PlanningShift AssignmentOptimizationDecision Support
Challenge

Connect three management levels in one model

Material flow, workforce availability and actual shift execution are traditionally planned separately. The goal is to turn them into consecutive inputs of one system while keeping the manager in control.

01

Material flow

Allocation and balancing of inbound and outbound flow across distribution centers, with control of planning-data freshness.

02

Workforce

Required capacity, availability schedules, roles, internal and external labor.

03

Shift assignment

Operation sequences, constraints, docks, employee availability and optimized schedules.

Solution architecture

Data → model → optimization → interface

The system gradually moves key logic from manual Excel planning into a reproducible digital environment.

Input data

Planned material flow, work schedules, operating standards and technological constraints.

Calculation layer

Balancing, resource calculation, constraint-based scheduling and constraint validation.

Data store

Versioning of data and results, history of plans and calculated assignments.

Management interface

Input updates, calculation launch and views by vehicle, employee and dock.

Project development

Stages and working updates

All news →

Block 1 — material-flow balancing

A flow-allocation model and a digital working environment for the result were created.

Block 2 — workforce planning

Flow was linked to required labor capacity, roles and actual availability intervals.

Block 3 — first shift assignment on real data

The working draft calculates operation sequences with roles, availability, docks and technological constraints.

Project principle

Do not automate assumptions

Debatable operating rules are validated in practice first. The mathematical model captures agreed logic; it does not replace it.